§ 21-174. Water system impact fee.


Latest version.
  • (a) A water system impact fee will be charged for the proposed new connection to the water system in accordance with sections 23-411 through 23-423 of this Code. For those customers residing within the utility service area, wherein service is available, a fee for water system expansion capital needs will be charged as provided in section 23-424.

    (b) Payment of the water system impact fee shall be made prior to connection to the water system.

    (c) The water system impact fee will be deposited into the Water System Impact Fee Trust Account immediately upon receipt. Impact fees deposited into said account shall be used solely for the purpose of constructing or improving the city's water system as provided in section 23-424.

(Ord. No. 2001-06, § 1, 5-15-01)

Editor's note

Formerly § 21-134.